Indices of the value of construction put in place, January 2025
The value of construction put in place up monthly and year-on-year
The value of construction put in place in January 2025 was 2.4% higher than in the previous month and 10.6% higher than a year ago.
The value of construction put in place higher than in the previous month …
At the monthly level, the value of construction put in place in January increased by 2.4%. As regards buildings, it went up by 31.2%, while as regards civil engineering and specialised construction activities it went down by 9.7% and by 0.2%, respectively.
… and higher than a year ago
At the annual level, the value of construction put in place in January increased by 10.6%. As regards buildings, it went up by 32.1% and as regards specialised construction activities by 26.2%, while as regards civil engineering it went down by 19.0%.
Tables with the latest data are available in the SiStat Database.
At the monthly level, the value of construction put in place in January increased by 2.4%. As regards buildings, it went up by 31.2%, while as regards civil engineering and specialised construction activities it went down by 9.7% and by 0.2%, respectively.
… and higher than a year ago
At the annual level, the value of construction put in place in January increased by 10.6%. As regards buildings, it went up by 32.1% and as regards specialised construction activities by 26.2%, while as regards civil engineering it went down by 19.0%.
Tables with the latest data are available in the SiStat Database.
Real indices of the value of construction put in place, Slovenia
Real indices of the value of construction put in place, Slovenia
|
METHODOLOGICAL NOTE
Data are seasonally adjusted.
Data for the last 6 months are provisional. With each release the data for this period can be corrected and supplemented with new data.
During the transition period after SKD 2025 (NACE Rev. 2.1) entering into force, statistical data will still be collected and published according to SKD 2008 (NACE Rev. 2). The transition periods will vary depending on the individual surveys.
Additional explanations are available in the methodological explanations.
Data for the last 6 months are provisional. With each release the data for this period can be corrected and supplemented with new data.
During the transition period after SKD 2025 (NACE Rev. 2.1) entering into force, statistical data will still be collected and published according to SKD 2008 (NACE Rev. 2). The transition periods will vary depending on the individual surveys.
Additional explanations are available in the methodological explanations.
When making use of the data and information of the Statistical Office of the Republic of Slovenia, always add: "Source: SURS". More: Copyright.